client="ca-pub-8105517493227625" data-ad-slot="" data-ad-format="auto">

GSurf Pro Setup and User Guide, Thank you for using Grandstream GSurf_Prov2 Network surveillance" class="text-sky-600 dark:text-sky-400 font-medium hover:underline" title="Guides for video surveillance">Video Surveillance System. Based on TCP/IP, Gsurf_Prov2 utilizes C/S architecture on distributed system, managing up to 10*36 channels. It can effectively reduce the network traffic and cameras’ workload by providing the transferring mechanism. Also, users could search and download the recording files remotely via the file management. Featuring functions of electronic map, preview, search, recording, alarm, playback, PTZ and etc., Gsurf_Prov2 is a powerful monitoring and recording system with intuitive interface as well as easy operation.

This user manual is designed to help you understand how to integrate your cameras and digital video servers with GSurf_Prov2 software.

Note

This document is subject to change without notice. The latest electronic version of this user manual is available for download here:

http://www.grandstream.com/support

Reproduction or transmittal of the entire or any part, in any form or by any means, electronic or print, for any purpose without the express written permission of Grandstream Networks, Inc. is not permitted.

PRODUCT OVERVIEW

Feature Highlights

◦ Built-in transfer server to forward the front-end real-time video streaming across network
◦ Capability to configure primary stream and secondary stream display according to the PC platform
◦ Embedded file sharing server for searching and downloading recorded files remotely
◦ PTZ control
◦ Integrated tools to synchronize time on the cameras, transform format for the recording files
◦ 72 channels video streams for group viewing or patrol mode
◦ Two-way audio/video monitoring and alarm
◦ Flexible alarm mechanism including relay output control and email alarm

https://documentation.grandstream.com/wp-content/uploads/2022/02/GSurf_Prov2-Overview.png

Figure 1: GSurf_Prov2 Overview

GSurf Pro Setup and User Guide

Read More : XMEYE VMS PC CLIENT Setup Guide

INSTALLATION GUIDE

Minimum Computer System Requirement

SERVER:

– Operating System: Windows 2003/2008 Server; Windows XP
SP2/SP3; Windows 7 32bit/64bit, Windows 8/10

– 
Processor: Intel® Core™ i3; 2.6GHz or above recommended
– 
Memory Capacity (RAM): 4GB or above
– 
Hard Drive Capacity: 320G (depending on video recording requirement)
– 
Graphics Card Type: Discrete Graphics Card (nVIDIA GEFORCE® GTX660 or above recommended)
– 
Network Adapter: 1000Mbps network adapter

CLIENTS:

– Operating System: Windows XP SP2/SP3; Windows Vista; Windows 7 32bit/64bit; Windows 8/10
–
 Processor: Intel® Core 2 Duo ™ or above
– 
Memory Capacity (RAM): 2GB or above
– 
Hard Drive Capacity: 120G (depending on recording requirement)
– 
Graphics Card Type: Discrete Graphics Card recommended
– 
Network Adapter: 100Mbps network adapter, 1000Mbps recommended

Note

UPS is required for SERVER to prevent database or video record file corruption caused by power outage.

Install Gsurf_Prov2

Click to run the GSurf_Prov2 installation .exe file. Follow the instructions in the prompted windows to start installation. Once done, the following screen will show.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9838.png

Figure 2: GSurf_Prov2 Installation

Uninstall Gsurf_Prov2

To uninstall GSurf_Prov2, in your windows PC Start Menu->Programs->GSurf_Prov2, click on Uninstall GSurf_Prov2 to start uninstall process. Or you could uninstall the program from your windows PC’s Control Panel.

Login Gsurf_Prov2

Click to run GSurf_Prov2. The login page will prompt for your User ID and Password. The administrator User ID and Password are both set to admin at the factory default settings.

For security purpose, please change the password after the first time you log in to GSurf_Prov2.

.

Figure 3: GSurf_Prov2 Login

Gsurf_Prov2 Main Window

The GSurf_Prov2 user interface is designed for ease-of-use to offer quick access to cameras and recording in the system. Please refer to the following figure and table for main window descriptions.

https://documentation.grandstream.com/wp-content/uploads/2022/02/GSurf_Prov2-Main-Window.pngFigure 4: GSurf_Prov2 Main Window

Table 1: Gsurf_Prov2 Main Window Items

1

Toolbar

Quick access to designated functions

2

Device Browser

View, add and manage devices; view electronic map

3

Video Display

Display up to 72 video streams. Double clicking on one video will display its primary stream in full window.

4

PTZ Control

PTZ control (PTZ device is required on the camera)

5

Log List

View operation log and alarm log

Gsurf_Prov2 Toolbar

Table 2: GSurf_Prov2 Toolbar Icons

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9841.png

Browse and manage the connected DVS or cameras

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9842.png

Open Electronic Map Browser. Right click to add a new map

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9843.png

Open Group View panel, manage groups and video channels.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9844.png

Open RS-485 panel for PTZ control

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9845.png

Display log list

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9846.png

Display alarm list

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9847.png

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9848.png

Choose different number of channels to be displayed on the main window (max number 72).

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9849.png

Open/hide play bar in each video display window.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9850.png

Send audio (broadcasting) to selected device in the list

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9851.png

Search all the cameras’ IP within the same LAN

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9852.png

Show GSurf_Prov2 software information

Gsurf_Prov2 Video Play Bar

In the video display window, each video channel has a play bar on the bottom.

https://documentation.grandstream.com/wp-content/uploads/2022/02/GSurf-Pro-V2-Video-Display-Window-Play-Bar.pngFigure 5: GSurf_Prov2 Video Display Window – Play Bar

Table 3: GSURF_Prov2 Video Play Bar Icons

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9854.png

Stop the displayed video in the channel

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9855.png

Start recording the video in the channel. By default, the recorded video file will be saved in directory C:\Record

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9856.png

Capture a snapshot of the current video in the channel. By default, the captured snapshot will be saved in directory C:\Snapshot

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9857.png

Turn on/off sound of the current channel. The default setting is off

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9858.png

Turn on/off two-way audio of the current channel. The default setting is off

CONFIGURATION GUIDE

After installing GSurf_Prov2, it must be configured for your network cameras or digital video servers. This section describes how to configure GSurf_Prov2, as well as how to set up auto recording, motion detection, alarms and etc.

Add/Delete Device

Add Device

1. In the top Menu bar, click System Config(C)->Device Config(D).

2. In the Device Configuration window, click Add button to open the Add Device dialog.

3. Enter the device information.

◦ Device Name: Enter a name for the device.
◦ Device Type: Select the device type, DVS or IPCAM.
◦ Count of channels: Select the number of channels that your device supports. For example, the GSC3610 has 2 channels.
◦ IP: Enter the IP address of the device.
◦ Domain Name: Enter the domain name of the device.
◦ Username/Password: Enter the Device’s Admin Credentials.
◦ RTSP Port: Enter the RTSP port for video streaming. If the device’s web access port is 80, enter 554 as RTSP Port. Otherwise, add 2000 to the device’s web access port and enter here.

4. Click Ok to save.

After successfully adding the device, users could view the video by double-clicking on the device name in the Device browser panel on the left.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9859.pngFigure 6: Add Device

Capture1Figure 7: Video Display After Adding Device

Delete Device

1. In the top Menu bar, click System Config(C)->Device Config(D).

2. In the Device Configuration window, Select the device to be deleted.

3. Click Delete button.

4. Or, users could click on Delete all to remove all the added devices.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9860.png

Figure 8: Delete Device

Search Device

The built-in Search tool in GSurf_Prov2 allows user to search all the DVS and IP Camera devices within the same LAN. Additionally, users could modify the IP address for the devices listed in the searching result.

Search Device

1. In the GSurf_Prov2 toolbar, click https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9861.png button.

2. In the Search tool, click Search button. A list of surveillance devices will display in the list.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9862.png

Figure 9: GSurf_Prov2 Search Tool – Search Devices

Configure Time Schedule

The GSurf_Prov2 time schedule is used to configure automatic recording. Up to 10 schedules can be configured.

1. In the top Menu bar, click System Config(C)->Time Schedule(T).

2. The Time Schedule window will pop up.

3. Select a schedule on the left panel to be configured.

4. Select the time frame for each day. The scheduled interval will be marked in blue (See Figure 10: Gsurf_Prov2 Time Schedule).

5. Click Save button.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9863.pngFigure 10: Gsurf_Prov2 Time Schedule

6. To assign this schedule to a device, open System Config->Device Config.

7. Select the device from which you would like to record the videos.

8. In Auto Record option, select schedule from the drop down list.

9. Click Save button.

This channel will then start automatically recording as specified in the designated time schedule.

Additionally, users could select Batch Configuration to assign the same time schedule to multiple devices.

https://documentation.grandstream.com/wp-content/uploads/2022/02/figure-11-GSurf-Pro-V2-Auto-Record-Time-Schedule-1024x699.pngFigure 11: GSurf_Prov2 Auto Record Time Schedule

Configure Alarm Triggers and Rules

Grandstream’s network cameras and digital video servers support motion detection and alarm events. They can report motion detection or alarm events to GSurf_Prov2. On the GSurf_Prov2 side, it can be configured to take actions, i.e., to notify such events to users. Up to 10 rules can be set up with different alarm actions. The instructions below will assist you with this setup.

1. In the top Menu bar, click System Config->Alarm Config.

2. In the Alarm action rule window, select the Alarm index and configure the action.

◦ Sound: If it’s checked, GSurf_Prov2 will play a sound when receiving an alarm report. Make sure to select a sound file and the duration for it to play.
◦ Warning on the E-map: If it’s checked, the corresponding icon of that channel in the electronic map will flash in red upon receiving an alarm report.
◦ Save to database: If it’s checked, the alarm event will be written to the alarm log.
◦ Record: If it’s checked, GSurf_Prov2 will record the video upon receiving an alarm report. Users could also select the duration for the recording.
◦ Pop up video window: If it’s checked, a pop up video window will appear on receiving an alarm report.

3. Click Save button to save the settings.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9865.png

Figure 12: GSurf_Prov2 Alarm Action Rule

4. To assign this alarm action rule to a device, open System Config->Device Config.

5. In the Device Configuration window, select the device.

6. Select an Alarm action rule for Motion Detection to monitor motion detection events. Or to Other Alarm for other types of conditions such as abnormal reboot.

7. Click Save button to save the settings.

https://documentation.grandstream.com/wp-content/uploads/2022/02/Figure-13-Assign-Alarm-Action-Rule-To-Device.pngFigure 13: Assign Alarm Action Rule To Device

Additionally, users could select Batch Configuration to assign the same alarm action to multiple devices.

Local Configuration

Click on System Config->Local Config to configure software and local recording features for GSurf_Prov2.

Software Configuration

Configure log reserved days, video window layout and startup options.

Record Config

◦ Record Path: This section displays name, total space and free space of the local disks. Users could select the local disk to store recorded video files. If users select multiple disks, GSurf_Pro will start from the first disk until the free space equals the reserved space, and then go to the next one.
◦ Reserved free space: Configure the reserved free space for the disk. When the disk free space is less than the reserved free space (1 GB in this example), the video will be recorded in the next selected disk.
◦ Record file duration time: Configure the duration for each recording file.
◦ Disk Full: When the disk is full, users could choose to stop recording, or keep recording while storing new recording by deleting the old files.
◦ Capture Path: Configure the path to save the snapshot pictures.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9867.pngFigure 14: GSurf_Prov2 Local Configure – Record Configure

Device Configuration

Click System Config->Device Config, the device configuration window will prompt for users to add, delete and edit devices. Once a device is selected, users could configure the device properties, alarm action rule and record option.

◦ Device Properties: Device Name, Device IP, Domain Name, RTSP Port and Transport protocol.
◦ Alarm Action Rule: Select alarm action rule for motion detection and alarm input.
◦ Auto Record: Select time schedule for auto record.

Language Display

In the GSurf_Prov2 interface, users could switch language at any time. Go to System Config->Language and select the language to be displayed.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9868.png

Figure 15: Language Display

Record Configuration

Manual Record

In the video display window, click on the Record button https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9869.png to start recording.

https://documentation.grandstream.com/wp-content/uploads/2022/02/Figure-16-Manual-Records.pngFigure 16: Manual Record

Automatic Record

The automatic record will be running in the background. The recording time is specified in Auto Record option after selecting device under System Config->Device Config.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9871.pngFigure 17: Automatic Record

Note

It is recommended to use continuous recording only and not combine it with recording by motion detection.

Replay

Both the GSurf_Prov2 Replay v2 (GXV36xx Models) and Replay v3 (For GSC36xx Models) tools provide the ability to replay recorded videos. These tools also provide a search function which allows you to perform a search based on start time, end time, IP address, channel and etc. To replay the recorded video, in the top Menu bar, go to Manage Tool->Replay Tool to open the Replayer. Select time, device, channel, file type and disk to search the video. Then click on the video file to play.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9872-1024x790.pngFigure 18: Replayer v3

In the Replayer, users could also open up the Time selection tab to specify the recorded files by filtering the start time. All the configured start time will be marked in green in the time chart.

Electronic Map

E-map is an important feature in video surveillance system to provide users a visual overview of the cameras in your installation. A map is an image file on which you place cameras and views. GSurf_Prov2 supports an electronic map for users to identify the locations of your cameras and the status of their alarms.

To configure E-map on GSurf_Prov2, open the map browser by clicking https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9873.png in the toolbar.

Add Map

1. In the Electronic map browser, right click and Add map option will show up.

2. Choose a map image from your local PC to upload. Then it will be displayed in the electronic map field.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9874.png

Figure 19: Add Map

Note

The supported image files are bmp, jpg or gif. GSurf_Prov2 will display the electronic map in full resolution. And the users can use the scroll bars to view the whole image.

Add Device to Map

1. Open your map in the main window.

2. In the left side panel, click on Device browser so your devices will show in the list.

3. Click on the device/channel, drag and drop it to the preferred destination on the map.

4. An icon with the device name and the channel number will now be shown on the map. Right click on the icon to change the icon settings.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9875.pngFigure 20: Add Map Alarm

Set Alarm on Map

1. After adding the device to the map, go to System Config->Alarm Config to configure alarm action rule. Make sure the option Warning on the E-map is checked.

2. Go to System Config->Device Config. Select your device and configure the alarm action rule set up in step 1.

3. When GSurf_Prov2 receives an alarm report, the corresponding icon on the map will flash in red .

Lock/Unlock Map

To avoid changing the positions of cameras on the map accidently, the users can lock the map after adding all devices.

Right click on the map, lock/unlock option will be available in the pop-up menu, When the map is unlocked, users could drag devices to the map. When the map is locked, double-clicking on the camera will open up a new window for real time video from this camera.

Remove Device from Map

On the map, right click on the icon and click Delete Icon to remove the device from the map.

Remote Configuration

The IP Camera devices can be remotely accessed via web browser. Select a device on the left side panel and click on Remote config tab to access the camera’s web GUI.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9876.pngFigure 21: Remote Configuration

PTZ Control

In the toolbar, click https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9877.png to open PTZ control panel. If the connected devices are PTZ cameras or have a PTZ device connected, users can use the console to adjust the focus, brightness, contrast, rotating speed, IRIS, and also pan/tilt the devices.

Note

Before using PTZ control, PTZ device needs to be set up in RS-485 port and properly configured.

Video Monitor

Individual View

Drag the device from the device browser to video display window to watch the video immediately.

Group View/Patrol Mode

1. In the tool bar, click on https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9878.png to open the Group view panel.

2. Drag the device in Device browser panel to the group in Group view panel.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9879.pngFigure 22: Add Device To Group

3. Right click on the group to configure the group attributes. Check the Allow Patrol option and configure Pause time which is the patrol interval for the group.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9880.png

Figure 23: Configure Group Attributes For Patrol Mode

4. Click Ok to save the settings.

5. In the top Menu bar, click on Play Mode->Patrolling View to start playing videos from different groups in a loop.

Synchronize Device Time

In the top Menu bar, click on Manage tool->Synchronize device time. Then users could sync up the device time with local PC time.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9881.png

Figure 24: Device Time Configuration

Convert Video Format

The recorded video is saved in H264 format, which might not be supported by certain video players. An AVI converter tool is provided in GSurf_Prov2. Click on Manage tool->AVI Conversion Tool to open the converter. Add video to be converted and the output file will be saved in the configured directory in AVI format.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9882.pngFigure 25: Media Convert Tool

User Management

The GSurf_Prov2 administrator can add, modify and delete users as well as issue users different privilege levels.

1. Click on Manage tool->User Manage.

2. In the User Manage window, users could add, edit and delete users. A list of configuration authorities is provided so each user could be assigned with different privileges.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9883.png

Figure 26: User Management

Import/Export Configuration

The GSurf_Prov2 configuration can be imported or exported for backup and restore purpose. Click on System Config->Export/Import Config to open the import/export window. Users could also select the configurations for the backup file.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9884.png

Figure 27: Configuration Import and Export

GSURF_PROV2 TRANSFER SERVER

The GSurf_Prov2 embedded transfer server can cooperate with client side to effectively reduce the workload on the front-end cameras. The surveillance system utilizes the transfer server as the medium to monitor the devices in a distributed manner.

Server Side

1. Open the Transfer server from Manage Tool->Tran Server. A login window will pop up.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9885.png

Figure 30: Transfer Server Login

2. After login, click on Config->System Config to open the following server configuration window. The listening IP address is the PC’s IP address. For the port number, it is recommended to use default value or big value.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9886.pngFigure 28: Transfer Server Configuration

3. Click on https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9887.png to open the search tool.

4. In the search tool, press Search button to get a list of devices in the same LAN.

5. Select the devices in the result list and click Add.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9888.pngFigure 29: Add Devices to Transfer List

6. Those devices will then be displayed in the transfer list.

The main display window will show the traffic status when the traffic starts.

Client Side

The client side is the GSurf_Prov2 RTSP server.

1. In the Device browser, right click on RTSP server.

2. Click Server Config to add devices to the local list.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9889.pngFigure 30: RTSP Server

GSURF_PROV2 FILE SERVER

Server Side

The file server can provide the record files in local disk to other hosts within the network for search, download and replay. To configure the GSurf_Prov2 as the file server, go to Manage Tool->File Server. Click on the Configuration button to set up listening IP and port. Then start the server.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9890.pngFigure 31: GSurf_Prov2 File Server

Client Side

The client side is the replay tool in the GSurf_Prov2. Go to Manage Tool->Replay Tool to open the Replayer. Once searching is done, the record files can be downloaded and played locally.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9891.png

Figure 32: Replayer Remote Search

HTTP SERVER

GSUpgrade Tool

This HTTP server allows user to configure a local HTTP server on the same machine running GSurf Pro which can be used to execute firmware update from this tool on IP Cameras either one by one or via batch upgrade by selecting them all. Go to Manage Tool->HttpServer. Click on the Configuration button to set up listening IP and port. Then start the server.

https://documentation.grandstream.com/wp-content/uploads/2021/12/word-image-9892-1024x779.pngFigure 33: GSurf_Prov2 HTTP Server

FREQUENTLY ASKED QUESTIONS

Q: How many cameras does GSurf_Prov2 support?

A: The GSurf_Prov2 can support up to 10 groups or 72 channels cameras at the same time. However, when using HD camera (720P and up), the maximum number might be limited by the PC processor. When displaying multiple videos, the GSurf_Prov2 will adjust the display to secondary stream to increase system resource efficiency. If users click on one of the video, the display will be automatically converted to primary stream for better quality.

Q: Does GSurf_Prov2 have any requirement on the PC where it’s installed?

A: Yes. Please refer to section [Minimum Computer System Requirement] for details. Before installing GSurf_Prov2, it is recommended to evaluate the system requirement (network traffic, disk space, file directory and etc.).

Q: Is there any requirement on the transfer server?

A: In most of the cases, the transfer server will have large amount of network flow going through. Therefore, it is recommended to use the machine with Gigabyte network interface card.

Q: What are the factors that might affect the disk space?

A: The disk space is mainly affected by the primary stream bit rate. Normally HD video will take more space than standard definition video.

Q: I have configured the alarm action on GSurf_Prov2 already but I still didn’t get alarm. Why?

A: Besides configuring alarm action on GSurf_Prov2 side, the alarm has to be activated on the camera side and configured to report to the alarm center. Users could configure this by directly accessing camera’s web GUI or via GSurf_Prov2’s remote configure interface.

EXPERIENCING THE GRANDSTREAM GSURF_PRO

Please visit our website: http://www.grandstream.com to receive the most up- to-date updates on firmware releases, additional features, FAQs, documentation and news on new products.

We encourage you to browse our product related documentation, FAQs and User and Developer Forum for answers to your general questions. If you have purchased our products through a Grandstream Certified Partner or Reseller, please contact them directly for immediate support.

Our technical support staff is trained and ready to answer all of your questions. Contact a technical support member or submit a trouble ticket online to receive in-depth support.

Thank you again for using Grandstream GSurf_Prov2 Network Video Surveillance System.

.

Advertisement In-Article Bottom Banner - Hardening Guides

Did this security guide help you?

Rate this article to help fellow engineers find the best guides.

Written by

Alex Vance

Senior Security Systems Architect & IoT Consultant with over 15 years in digital surveillance design.

Discussion (0)

No comments yet. Be the first to share your thoughts!

Leave a Comment